wiz-icon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

Consider a PERT network for a project involving six tasks (a to f)

Task Predecessor Expected task time (in days) Variance of the task time (in days2)
a - 30 25
b a 40 64
c a 60 81
d b 25 9
e b, c 45 36
f d, e 20 9

The expected completion time of the project is

A
238 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
224 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
171 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
155 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution

The correct option is D 155 days
PERT networks are:



Here we see that expected completion time of the project is 155 days and critical path is a-c-e-f

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Mean Deviation about Mean for Discrete Frequency Distributions
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon